A status colour you can argue with

Every indicator traces to a number and states the threshold that produced it. Overall is the worst of its parts. The narrative is yours — nothing here is written for you.

HomeProject Management › Status Report

A status report where every colour traces to a number

Indicators are derived and state their thresholds. The narrative is yours and is never generated.

Local tool — your project data stays in your browser

Milestones

Open risks and issues

Milestones

Your project stays in this browser. Task names, owners, durations, dates and estimates are calculated on your own device. Nothing is uploaded, stored on a server, or included in analytics — project content is never passed to the advertising or analytics scripts on this page.
How the indicators are derived

variance = (forecast − planned) ÷ planned, for both schedule and cost. Green below the amber threshold, amber between, red above the red threshold.

Overall is the worst of its parts, and cannot be talked up. A milestone forecast late or an open high-severity risk pushes it off green regardless of what the other indicators say.

Thresholds are yours. A 5% schedule variance is serious on a two-week sprint and noise on a three-year programme, so the defaults are meant to be changed.

No narrative is generated. The indicators say what is happening; only you can say what it means.

Why the colour must trace to something

A status colour chosen by feel is the mechanism by which a project reports green for three months and then slips a quarter. Nobody lies; each individual judgement is defensible; and the aggregate is a fiction.

An indicator derived from numbers, showing the threshold that produced it, can be argued with. That is the point — a report that cannot be challenged cannot be trusted either.

Overall cannot be talked up

The most common corruption is an overall status better than its components: two ambers and a red producing an overall amber because the conversation was difficult. Here the overall is the worst of its parts, and a late milestone or open high risk pushes it off green on its own.

A report with no ask is not a report

If the project is not green and nothing is being asked of the reader, you have told someone about a problem they cannot help with. That is a briefing, and it trains people to skim.

The decisions section is where a status report earns its place: this is what I need from you, this week, to keep this on track.